Explainer - moving to an integrated delivery model

12 Dec 2024


Unsure what an Integrated Delivery Model for NZ’s state highway road maintenance network might look like? Check out the latest explainer from CCNZ Technical Manager Michelle Farrell, below!

Seventeen new road maintenance contracts around the country will be tendered in early 2025. The plan is for tenders to be released in February, with a closing date in May. These new contracts – referred to as Integrated Delivery Contracts (IDCs) – could be in place for up to 10 years.

So, first of all, why would NZTA want to tender all of these 10-year road maintenance contracts in one go? The reasoning behind this decision is to provide certainty of a pipeline of work, enabling companies to plan where to allocate resources and training.

While it might not appear to support inclusion of smaller players into the market, it takes a wider view of the supply chain while providing certainty to the market.

That leads to the next piece of the puzzle – ‘contestable work’ and the ‘Directory.’

What is contestable work?
"Contestable work" refers to tasks that can be competed for by different companies other than the incumbent IDC supplier. This ensures that no single company has control of all the work, allowing others to bid to offer the same service, often to try to do it better or at a lower cost.

The graph below shows how NZTA plans to treat different portions of the work from 2025 onwards. A large portion of maintenance work is core IDC scope activities – the bread and butter for the main contractor awarded one of the 17 new IDCs.

The top portion is packages of work made contestable through the Directory.

This leaves the two portions of “potentially contestable work,” which could include pavement rehabs and/or renewals, pavement marking, and/or environmental (drainage) renewals.

How will the ‘potentially contestable’ work be allocated?
The IDC holder will be allocated the majority of ‘potentially contestable’ work at the start of the contract tenure. However, a percentage of this work will be held ‘at risk’ based on performance. If the IDC holder underperforms, the ‘at risk’ component will be made available to the Directory. Conversely, if the IDC holder demonstrates outstanding performance, some of this contestable work may be directly awarded to them.

Subcontracting requirements
The IDC contracts will also retain a requirement that a portion of the work be subcontracted. This requirement is applicable across all work undertaken by the IDC supplier, even though it is not explicitly referenced in the graphs.

Will the IDC holder be able to bid for Directory work?
This is yet to be finalised and may vary by region, depending on the strategic direction NZTA wishes to take and the availability of resources within each region.

What about core work?
Core work includes everything you would expect from a standard road maintenance contract, including cyclic activities, incident response, reactive maintenance and renewals.

The distinction between core work and contestable work will change over time based on government priorities, reflected in Government Policy Statements and the National Land Transport Programme. Contestable work is essentially work activities with programmes that are larger than what the IDC holders, as a collective, can deliver.

What does ‘integrated delivery’ mean?
Integrated delivery implies closer collaboration among various stakeholders – almost working shoulder-to-shoulder. However, NZTA has emphasised its intention to provide firmer direction in strategic asset management, such as deciding what work needs to be done on the network and when. The delivery of work, however, will be more collaborative, involving NZTA and contractors working together to optimise programmes and ensure efficient, effective delivery.

NZTA will lead programme management to align and sequence all activities – whether undertaken by the IDC supplier, Directory suppliers, third parties, or capital projects. This approach aims to optimise network use and minimise customer impact.

In summary, NZTA’s 2025 procurement framework represents a significant shift towards collaboration and performance-based outcomes, with clear roles for both core and contestable work. This framework seeks to balance efficiency, innovation, and effective delivery while maintaining flexibility to adapt to regional needs and contractor performance.

 

 

RELATED


Principal Business Partner
Core Associates
Major Associates
ALH LTD
AWF
Portacom New Zealand Limited
Global Survey - Auckland
Humes Pipeline Systems
n3
Teletrac Navman
Westpac NZ Ltd
XCMG New Zealand
Porter Group Limited
Employment Hero
TR Group
AEL
Brolube New Zealand
Assignar
Youngman Richardson
Hydraulink Fluid Connecters Ltd
SITECH NZ
Commercial Hire NZ Ltd
TLC Insurance Limited
Brandt Equipment
Infrastructure New Zealand
SAMI Bitumen Technologies Pty Ltd
Vertu Equipment Limited
Solo
Central Group Forklifts & Trucks
beforeUdig
MIMICO NZ Ltd
UDC Finance
Franklin Smith Group
CivilShare
The Drug Detection Agency
First Gas
Over and Out Communications
Firth Certified Concrete
Vertical Horizonz NZ Ltd
Rettenmaier New Zealand Ltd
Geosynthetic Partners International Ltd
A B Equipment Ltd
Aptella
Marley NZ Ltd
MBP (NZ) Ltd
Steelgal NZ Ltd
H.J. Asmuss & Co. Ltd
RobLawMax Recruitment
Blick
Winstone Aggregates
CSP Div of Fletcher Steel
TVH NEW ZEALAND
Wirtgen NZ Ltd
MATES In Construction
Geofabrics New Zealand Ltd
ERoad Ltd
Southeys Group Auckland
Prime Fluid Management
Liebherr New Zealand
AECOM New Zealand Limited
Sheet Pile Ltd
Fluiconnecto Ryco New Zealand Ltd
Komatsu New Zealand Ltd
Northpine Ltd
Checksafe Ltd
Milwaukee Tool New Zealand
Terra Cat
Power Farming New Zealand Ltd
Greenlight Insurance Brokers
Absolute Immigration NZ
RB Recruitment
Doug the Digger
Turners Group Ltd: Head Office/Auckland
Trade Me Jobs
Enviro NZ Services Ltd
New Zealand Transport Agency
John Deere Limited
Reliance Reinforcing Limited
Rimkus
Hynds Pipe Systems
ENZED
Terra Infrastructure Pty Ltd
Advice Financial
Infrastructure Sustainability Council
Connexis
TotalEnergies NZ Ltd
Kobelco New Zealand
TRIG Instruments
Mico New Zealand Ltd
Manage Company
Holcim New Zealand Ltd
BNZ Partners
Parallaxx
Nulca NZ
TDX Ltd

Login





Forgot password?
Create an Account