The Omanawa Bridge Replacement is a $42 million infrastructure project delivering a new bridge crossing and associated road realignment to improve safety, resilience, and future-proof this important transport link for the region.
The project is being delivered over a 21-month construction programme, with HEB Construction self-performing a significant portion of the works, including civil earthworks, bridge structures, and pavement surfacing.
Join us for a site visit on Thursday 23th July 2026
Registration required. Registered attendees will be provided with additional information to ensure you can safely access the site.
Time: 3:00pm
Parking: Parking is limited, so carpooling would be appreciated where possible.
PPE Requirements: Please bring steel‑toe boots, long pants, a hard hat, and high‑visibility clothing. Spare hard hats and hi‑vis vests available for anyone who needs to borrow them.
Site Tour: Sean Pearce, PM, will lead the tour and will be available to answer any questions. Please note the tour will not cover the full site, as piling operations will be underway.
BBQ: Hirepool are kindly supporting the team with a BBQ onsite.
A big thanks to HEB and Hirepool.
Registration required. If you are unable to register online, then please email Kat at bayofplenty@civilcontractors.co.nz